Renovation of Most Holy Trinity Catholic Chapel Tower United States Military Academy, West Point, NY
CURRENT PERFORMANCE & REFERENCE SHEET
| Project Name & Location: |
Renovation of Most Holy Trinity Catholic Chapel Tower United States Military Academy, West Point, NY |
| Client Name & Address: |
USACA, U.S. Military Academy, Dir. of Contracting Bldg. 681, USMA, West Point, NY 10996-1594 |
| Contract Number: |
W911SD-07-D-0006-0002 |
|
|
| Date of Contract: |
08/28/07 |
Contractual Completion: |
02/15/09 |
| Date work was started: |
03/03/08 |
Actual Completion: |
01/12/09 |
|
|
|
|
| Description of Contract Work: |
|
Work included Deconstruction and Reconstruction of the Catholic Chapel Tower including:
- Deconstruction & salvage for reinstallation: granite and veneer stones and limestone, existing copper clad louvers, church bell, speaker platform and access hatches.
- Removal and Disposal of: misc. exterior limestone pieces, interior brick veneer, roofing systems and temporary steel.
- Reconstruction included: Cast-in-Place concrete frame, granite veneer, new limestone pieces to match original, tower masonry walls, reinforcement of the steeple, two new modified bitumen roofs and replacement of roof hatches.
Trades Included:
 |
 |
| Placement of Ashlar Stone at Outside Corner |
Limestone Restoration |
| |
|
 |
 |
| Pointing Ashlar Stones |
Belfry Tower Wall |
| |
|
 |
 |
| Coping Stone Restoration |
Chapel Tower | |